If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

What is the slope of the line (-7,2) (4,6)
if rs 900 amounts to rs 1044 in 4 years, what sum will amount to 1368 in 3 1/2 years at the same rate
How are deposits reflected in a balance sheet? What are they known as?
For [tex]f(x) = 4x + 1[/tex] and (x) = [tex]g(x)= x^{2} -5,[/tex] find [tex](\frac{g}{f}) (x)[/tex]A. [tex]\frac{x^{2} - 5 }{4x +1 },x[/tex] ≠ [tex]-\frac{1}{4
A water tank holds 18000 gallons. How long will it take for the water level to reach 6000 gallons if the water is used at anaverage rate of 450 gallons per day
Which image shows labeled organelles that are present ONLY in plant cells?
[WILL GIVE BRAINLIEST- 50 POINTS] Please answer these questions to the best of your ability. Merci! 1) What is the imperative tense used for? 2) When do y
What is the similarity ratio of a cube with volume 729m^3 to a cube with volume 3375 m^3
what is the measure of angle x? PLEASE ANSWER
What fraction is equivalent to 0.46464646··· A. 46⁄99 B. 46⁄999 C. 46⁄100 D. 23⁄50