15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

why does bread dough is needed to be left for hours or a day before baking?​
Which represents the inverse of the function f(x) 4x? O h(x) = x + 4 O h(x) = x - 4 O h(x) Sx O h(x) = ~x
A student graphed distance versus time for an object that moves 14m every 2 s. the speed of the object is
Plot the graph of 2x - y = 6 and y = 4. Write down the coordinates of the point where the lines intersect
A student graphed distance versus time for an object that moves 14m every 2 s. the speed of the object is
Complete the sentence with a word that means the same as "rare"
Cuanto vale la y en matemáticas
adeshinaquadrioluseg Don't look at this users questions they are literally all wrong Trash
Kara is running a marathon. After 2 hours, Kara has run 13 miles. After 4 hours, Kara has run 26 miles. What is her speed, in miles per hour?​
100° 100⁰ X = ??????