If 10 workers, working for 4 hours complete the work in 12 days, in how many days will 8 workers working for 6 hours complete the same work?

Respuesta :

mariyamzuha123
mariyamzuha123 mariyamzuha123
  • 03-05-2021

Answer:

As per the question, 10 workers working for 4 hours a day complete their work = 12 days. 1 person working for 1 hour a day complete the work = 12×10×4 days. Thus, the 8 persons working for 6 hrs a day complete their work in 10 days.

Step-by-step explanation:

hope it helps

please mark brainliest

Answer Link

Otras preguntas

what does the surface area represent in a cell
what is the time interval between the release of the ball and the time it reaches its maximum hieght? the acceleration gravity is 9.81m/s^2 and the maximum heig
why does methane have a low boiling pint?
A person walks 25 m west and then 45 m at the angle of 60 degrees north of east what is the magnitude of the total displacement?
Find the value of 2 in this equation. 33- (8t) = 15
what does the surface area represent in a cell
E = mv^2 Work out the value of E when m = 3 and v = 10
results of 1+2+3+....+99+100+99+...+3+2+1 is.....
What phylum has animals with a central cavity and mouth;and most of them have tentacles?
Find the value of 2 in this equation. 33- (8t) = 15