how do you find the mean completion time of a PERT network diagram?​

Respuesta :

okekesarah01642112
okekesarah01642112 okekesarah01642112
  • 02-01-2021

Answer:

PERT is an estimating technique that uses a weighted average of three numbers (see below) to come up with a final estimate. The resulting PERT estimate is calculated as (O + 4M + P)/6. This is called a "weighted average" since the most likely estimate is weighted four times as much as the other two values.

Answer Link

Otras preguntas

How long does it take for pending paypal donations to go through?
What river is important as the transportation routes in source of hydroelectric power in russia and is the longest river in europe?
Question 1 Unsaved How does the drama of A Midsummer Night's Dream resolve? Question 1 options: Everyone is miserable and goes their own separate ways Everyone
Which element of an argument must be supported with evidence? A. Claims B. Conclusions C. Reasoning D. Assumptions
which is a complex sentence?
Which equation matches the graph shown below?
what is the domain and range of y=x
jurisdiction means the
Taylor and Jesse are buying a magazine for $3.75 and a snack for $2.49. If they split the total cost between the two of them, how much will they each pay?
Which of the following represents the graph of f(x) = 3x + 1