Estimate the quantity of soil to be excavated from the borrow pit​

Respuesta :

lola2487
lola2487 lola2487
  • 04-08-2019

Answer

1056

Explanation:

for example

A soil is to be excavated from a borrow pit which has a density of 1.75g/cc and water content of 12%. The G is 2.7 the soil is compacted to that water content of 18% and dry density of 1.65g/cc. for 1000 m3 of soil used in fill estimate

Quantity of soil to be excavated from pit in m3

Answer Link

Otras preguntas

rational number between 1/8 and 1/4
how did gold help create a strong economy in the kingdom of ghana
A 2-kg object is moving horizontally with the speed of 4m/s. How much net force is required to keep the object moving at this speed in this direction?
What happened in 1853 that showed Japan the importance of industrial power?
a box of 10 markers weighs 105 grams. if the empty box weights 15 grams, how much does each marker weigh?
Which statement best illustrates ideals that reflect socialism?
there are 3 trays of eggs each tray holds 30 eggs.how manny people can be served if each person eats 2 eggs
the biomolecule whose function is short-term energy storage
a model car has a scale of 3 cm : 2 m. The length of the actual hood of the car is 1 m. What is the length of the model?
Corey needs 24 boards that are 47 1/2 long. How many feet of boards should he buy